Roof replacement with solar panels needs a joined-up plan before either trade starts. The roofer needs access to the roof covering, while a competent solar specialist must deal with the electrical system and panel handling.
For a full replacement beneath an existing array, plan for the affected panels to come off and return later. However, confirm the exact scope after a survey. Clear responsibilities help prevent gaps between panel removal, weatherproofing and the final system checks.

Start with one survey brief for both trades
First, tell the roofer that solar panels are already in place. Share photographs, the installation date if known and any existing roof report. Also, explain whether you want to keep the array unchanged or discuss alterations.
Next, gather the solar paperwork. Useful documents include the original installer details, system layout, equipment information and warranty terms. If another organisation owns the panels, establish its requirements before arranging removal.
The roofing and solar teams should then agree what they need to inspect. Some roof areas may remain concealed until the panels come off. Therefore, ask how they will record discoveries and approve additional work before it proceeds.
This early discussion should identify a contact who coordinates both work schedules. Otherwise, a change to one booking can leave the other team waiting.
Agree the scope of roof replacement with solar panels
Avoid a quote that simply says “remove and refit solar”. Instead, ask for a clear division of tasks.
The written scope should explain who handles:
- Safe electrical work and the system shutdown arrangements.
- Panel removal, labelling, lifting and transport.
- Secure storage and protection during roofing work.
- Removal or replacement of brackets and mounting components.
- Roof preparation and weather protection between visits.
- Reinstallation, testing and handover records.
Also, ask who checks the suitability of the mounting system for the new roof covering. Reusing the panels does not automatically mean every fixing can return unchanged.
If the proposals differ, compare them task by task. A roofing price with no allowance for solar handling is not directly comparable with a combined quotation.
Plan roof access around the solar panels
Do not climb onto the roof, disconnect cables or move panels yourself. Electrical isolation and roof access require competent planning. HSE’s electrical refurbishment guidance explains the need for trained people and safe isolation procedures.
Meanwhile, ask both teams whether the proposed access suits their work. The scaffold arrangement must support the planned activities, rather than simply reach gutter level. HSE’s roof-work guidance identifies access and preventing falls as key planning issues.
For example, discuss how the team will move panels from roof level to their storage area. Also identify narrow side passages, conservatories or parked vehicles that affect access. These details belong in the survey brief before the scaffold arrives.
Set a sequence with clear handover points
Roof replacement with solar panels involves more than two separate installation dates. Ask for a programme that connects the following stages.
Before the solar panels leave the roof
The solar specialist should confirm the planned electrical arrangements. Also agree how the team will record the existing equipment and any visible damage. This gives everyone a shared starting point.
While the roofing work takes place
Keep the storage area secure and outside normal household traffic. Ask who remains responsible for the equipment throughout this period. Meanwhile, the roofer should explain how the roof will be protected between work stages and during unsuitable weather.
Before the array returns
Agree a checkpoint for the completed roof areas and the mounting details. The solar team should know when those areas are ready, rather than arriving on an assumed date.
Before the project closes
Ask for the agreed system checks and a clear handover. The Energy Saving Trust’s installation guide describes testing and showing householders how to monitor generation as part of post-installation support. For your refitted system, agree the checks and records with the solar specialist in advance.
Discuss downtime, warranties and possible changes
During roof replacement with solar panels, allow for a period without normal solar generation. Ask when shutdown starts and what could affect the planned restart. However, avoid treating an initial programme as a guarantee against weather or hidden roof defects.
If you have a battery, ask the specialist what the work means for its operation. Do not assume it will continue to work in the usual way while the solar system is disconnected.
Similarly, check the warranty position before dismantling. Ask whether the existing installer or manufacturer sets conditions for removal, storage or refitting. Confirm who warrants the new roofing work and who covers the solar work.
If you want extra panels or a layout change, raise that separately. The installer may need to review the design and relevant notifications. Keeping that decision explicit prevents an agreed refit from becoming an unpriced system upgrade.
Check the roof and solar panels at handover
Before closing the project, request a simple list of the records you will receive. These may include roofing warranty information, photographs, details of changed mounting components and the solar specialist’s test or commissioning records.
Also ask the installer to demonstrate the monitoring system. If the display shows a fault or the readings seem unexpected, report it promptly. Output varies with conditions, so a single reading alone cannot prove that everything works correctly.
Finally, keep the documents together with the original solar paperwork. Include the names of both contractors and the person to contact about each part of the work.
Arrange a roof assessment in Nottingham
Premier Roofing Solutions provides residential roofing and solar panel installation services in Nottingham and surrounding NG postcode areas. Share your existing system details when discussing the project so the team can assess the roof and explain the required scope.
For the roofing portion, the roof replacement cost guide outlines the factors that affect a quotation. Solar removal and reinstatement need their own clear allowance. A coordinated survey is the starting point for roof replacement with solar panels that accounts for both systems.